Borealis Project
Expand natural gas delivery capacity between Ohio and Kentucky to help meet growing regional energy demand
Support communities, utilities, and industrial user energy needs by adding new system capacity
Use existing utility and pipeline corridors whenever possible to minimize environmental impact and support long‑term system reliability
This project is in the early development and stakeholder engagement phase.
Project overview

Proposed Borealis Project Details:
The Borealis Project is in the early‑phase of project development, wherein stakeholder engagement and landowner survey permission activities are taking place. These activities help us determine a viable route option thanks to on-the ground inspections and feedback from local officials.
While the scope is still being finalized, there are two main components of the Borealis project we plan to focus on:
Borealis Mainline Pipeline:
- Approximately 265 miles of new natural gas pipeline from Ohio to Kentucky
- 1.75 Bcf/d of additional natural gas capacity
- 79% of the pipeline route is proposed to be built alongside existing utility corridors
- Additional compression at our existing station in Indiana
Borealis Supply Leg Pipeline:
- Approximately 200 miles of new natural gas pipeline in Ohio
- 2 Bcf/d of additional natural gas capacity
- 96% of the pipeline route is proposed to be built alongside existing utility corridors
- Two new compressor stations in Ohio
Project Timeline
The project follows a multi-year federal review and development process designed to encourage public involvement, environmental review, and transparency at every stage. Dates shown are anticipated and may adjust as the project advances.
Public Engagement & Early Planning (2026)
The process begins with early public engagement as part of the Federal Energy Regulatory Commission (FERC) Pre Filing Process. During this phase, the project team shares preliminary information, gathers input from landowners, agencies, and stakeholders, and refines project concepts.
Pre-Filing with FERC (Second Half of 2026)
The Pre-Filing Process allows the project team to work closely with FERC to:
- Refine the proposed route and facilities
- Coordinate environmental studies
- Conduct stakeholder and agency outreach
- Prepare materials for the formal application
FERC Application Submitted (Second Half of 2027)
A formal application under Section 7(c) of the Natural Gas Act is filed with FERC. This application includes:
- Detailed project description and proposed route
- Environmental reports
- Technical and engineering information
Environmental Review & Public Comment (2027–2028)
FERC conducts an Environmental Impact Statement (EIS) in accordance with the National Environmental Policy Act (NEPA). During this time:
- Landowners, agencies, and the public may submit comments
- Stakeholders may formally intervene in the process
- FERC evaluates potential environmental and community impacts
FERC Order & Certification (Second Half of 2028)
If approved, FERC issues an order granting a Certificate of Public Convenience and Necessity, which authorizes construction of the project.
Construction (2028–2029)
Following certification, construction activities may begin. Landowners directly affected by construction would be contacted by project Land Agents to discuss schedules, access, and property specific details.
Project In Service (Second half of 2029)
Construction is completed and the project is placed into service, marking the end of the development and construction phase.
This timeline is provided for informational purposes and reflects current planning assumptions.
Preliminary Pipeline Route
The Borealis Project pipeline route is not final and may change based on survey results, or engineering and environmental studies. Once the project is further developed, more detailed maps will become available.
.jpg)
Resources for General Natural Gas Project Understanding:
Stakeholder Engagement
Boardwalk is committed to fostering effective and constructive communication with stakeholders throughout every phase of a project. Key elements of the stakeholder engagement for the project include:
- Coordination with political leaders: Early engagement with local elected officials is a priority for ensuring they are informed and involved from the outset.
- Feedback and transparency: Stakeholder input is actively encouraged and valued. Boardwalk strives to provide clear, transparent responses to questions and concerns.
- Ongoing dialogue: Two-way communication is essential. Boardwalk maintains open lines of dialogue with stakeholders throughout the lifecycle of each project to build trust and ensure mutual understanding.
Safety & Environmental Commitment
Boardwalk is committed to safety, environmental stewardship, and regulatory compliance. The Borealis Project reflects this commitment through the following measures:
- Regulatory oversight: Boardwalk operating subsidiaries are interstate natural gas pipeline companies regulated by the Federal Energy Regulatory Commission (FERC).
- Design and operation standards: The Borealis Project will be designed and operated in compliance with all applicable federal and state safety and environmental regulations.
- Environmental compliance: Project facilities will meet established federal and state standards for noise and air quality, ensuring minimal impact on surrounding communities.
Natural gas safety & benefits
Natural gas pipelines are an important part of the United States energy system, playing a critical role in meeting growing energy demands. We are proud to work in an industry that sustains America’s energy advantage by providing secure, affordable and low-carbon energy that powers communities and supports progress. We are committed to providing safe and reliable services while protecting the environment and the surrounding communities. This commitment is made to our customers, employees, and the communities in which we operate as we incorporate environmental stewardship, safety, and compliance into our day-to-day operations.
Economic Benefits
Boardwalk contributes significantly to local economies through taxes, jobs, and infrastructure investment. The Borealis Project is expected to increase tax revenue in participating counties and support local services.
Project overview

Proposed Borealis Project Details:
The Borealis Project is in the early‑phase of project development, wherein stakeholder engagement and landowner survey permission activities are taking place. These activities help us determine a viable route option thanks to on-the ground inspections and feedback from local officials.
While the scope is still being finalized, there are two main components of the Borealis project we plan to focus on:
Borealis Mainline Pipeline:
- Approximately 265 miles of new natural gas pipeline from Ohio to Kentucky
- 1.75 Bcf/d of additional natural gas capacity
- 79% of the pipeline route is proposed to be built alongside existing utility corridors
- Additional compression at our existing station in Indiana
Borealis Supply Leg Pipeline:
- Approximately 200 miles of new natural gas pipeline in Ohio
- 2 Bcf/d of additional natural gas capacity
- 96% of the pipeline route is proposed to be built alongside existing utility corridors
- Two new compressor stations in Ohio
Project Timeline
The project follows a multi-year federal review and development process designed to encourage public involvement, environmental review, and transparency at every stage. Dates shown are anticipated and may adjust as the project advances.
Public Engagement & Early Planning (2026)
The process begins with early public engagement as part of the Federal Energy Regulatory Commission (FERC) Pre Filing Process. During this phase, the project team shares preliminary information, gathers input from landowners, agencies, and stakeholders, and refines project concepts.
Pre-Filing with FERC (Second Half of 2026)
The Pre-Filing Process allows the project team to work closely with FERC to:
- Refine the proposed route and facilities
- Coordinate environmental studies
- Conduct stakeholder and agency outreach
- Prepare materials for the formal application
FERC Application Submitted (Second Half of 2027)
A formal application under Section 7(c) of the Natural Gas Act is filed with FERC. This application includes:
- Detailed project description and proposed route
- Environmental reports
- Technical and engineering information
Environmental Review & Public Comment (2027–2028)
FERC conducts an Environmental Impact Statement (EIS) in accordance with the National Environmental Policy Act (NEPA). During this time:
- Landowners, agencies, and the public may submit comments
- Stakeholders may formally intervene in the process
- FERC evaluates potential environmental and community impacts
FERC Order & Certification (Second Half of 2028)
If approved, FERC issues an order granting a Certificate of Public Convenience and Necessity, which authorizes construction of the project.
Construction (2028–2029)
Following certification, construction activities may begin. Landowners directly affected by construction would be contacted by project Land Agents to discuss schedules, access, and property specific details.
Project In Service (Second half of 2029)
Construction is completed and the project is placed into service, marking the end of the development and construction phase.
This timeline is provided for informational purposes and reflects current planning assumptions.
Preliminary Pipeline Route
The Borealis Project pipeline route is not final and may change based on survey results, or engineering and environmental studies. Once the project is further developed, more detailed maps will become available.
.jpg)
Resources for General Natural Gas Project Understanding:
Stakeholder Engagement
Boardwalk is committed to fostering effective and constructive communication with stakeholders throughout every phase of a project. Key elements of the stakeholder engagement for the project include:
- Coordination with political leaders: Early engagement with local elected officials is a priority for ensuring they are informed and involved from the outset.
- Feedback and transparency: Stakeholder input is actively encouraged and valued. Boardwalk strives to provide clear, transparent responses to questions and concerns.
- Ongoing dialogue: Two-way communication is essential. Boardwalk maintains open lines of dialogue with stakeholders throughout the lifecycle of each project to build trust and ensure mutual understanding.
Safety & Environmental Commitment
Boardwalk is committed to safety, environmental stewardship, and regulatory compliance. The Borealis Project reflects this commitment through the following measures:
- Regulatory oversight: Boardwalk operating subsidiaries are interstate natural gas pipeline companies regulated by the Federal Energy Regulatory Commission (FERC).
- Design and operation standards: The Borealis Project will be designed and operated in compliance with all applicable federal and state safety and environmental regulations.
- Environmental compliance: Project facilities will meet established federal and state standards for noise and air quality, ensuring minimal impact on surrounding communities.
Natural gas safety & benefits
Natural gas pipelines are an important part of the United States energy system, playing a critical role in meeting growing energy demands. We are proud to work in an industry that sustains America’s energy advantage by providing secure, affordable and low-carbon energy that powers communities and supports progress. We are committed to providing safe and reliable services while protecting the environment and the surrounding communities. This commitment is made to our customers, employees, and the communities in which we operate as we incorporate environmental stewardship, safety, and compliance into our day-to-day operations.
Economic Benefits
Boardwalk contributes significantly to local economies through taxes, jobs, and infrastructure investment. The Borealis Project is expected to increase tax revenue in participating counties and support local services.
Key project components
Construction / operation / safety
Environmental considerations
Construction updates
There are no construction updates at this time, as construction for the Dearborn County Lateral Project is anticipated in 2027.
Landowner Inquiries (For individuals directly involved with facility siting or for individuals who would like to know if their property is impacted):
(844) 652-6731
Community Affairs (For local community members interested in more information):
Payton Barrientos
Phone: (832) 570-6277
Email: payton.barrientos@bwpipelines.com
Government Affairs (For local and state elected officials):
Josie Hammon
Phone: (502) 612-9494
Email: josie.hammon@bwpipelines.com
Matt Hammond
Phone: (614) 738-6123
Email: mhammond@orion-strategies.com
Media Inquiries (For reporters, news stations, etc.):
Boardwalk's Borealis Project Press Release
Phone: (866) 913-2122
Email: PR@bwpipelines.com
Customer Inquiries (For companies interested in capacity from this project):
Julianna Loucks, Director Business Development
Phone: (270) 688-6942
Email: julianna.loucks@bwpipelines.com
Anthony Saputo, Director Business Development
Phone: (713) 479-8026
Email: anthony.saputo@bwpipelines.com






